The Beach Front: Update September 2018

Blocks C & D

Works are so very near to completion now, with phase 2 of the furniture being fitted; sofas, bed mattresses, curtains, and loose kitchen equipment. We are in the final stages of the touching up and making good.

To block D there is a corridor safety wall to be built on each level. This is ongoing, starting at the lower levels.

To the pool terrace area, there is some decking to be installed. This will happen late next month.

In the basement, the back of house and fitness center works are ongoing.

Block F

Block F is moving on very nicely. Well-coordinated works are paying off with much faster progress.

We have the furniture teams working from the lower floors up.

The electrician and plumbing teams are working above them.

Balcony glass works are coming together nicely.

Kitchens will start next week after being coordinated with the furniture works.

The basement kitchen works are also proceeding well, and will be commissioned shortly.

Villas

The villas are not as moving as we would like but with ongoing progress will be completed.

Furniture works are ongoing.

X-Suites

Ceilings installed.

Ceilings and walls being painted.

Plunge pool tiling is complete.

Update August 2018

Blocks C & D

Except for some final tuning and making good, everything is done for block C.

There are some rectification works ongoing to the corridors, and some final making good.

To the exterior for block C facing the swimming pool, we are designing a screening or similar to improve the look of the block.

Basement works are still ongoing. We can confirm a completion date in the near future.

Block F

Block F is still 6 weeks behind but is now moving at a good pace.

Terrace doors and windows are being installed.

Internal glass doors and dividers are near completion.

Furniture and kitchens are all manufactured and are the next thing to go as tiling, painting, and sanitary wares are all so close to being done.

AC fan coil units are also near completion.

All is looking good at block F.

X-Suites

Works are progressing, but not as quick as Block F.

Be reminded that these units are not as much work as Block F, and now the ceiling, wall works, and tiling are ongoing, even though a bit behind schedule, we believe we can make up for lost time.

Villas

The works to the Villas are not far from completion.

Ceilings, and flooring works are done. Once the kitchen and furniture works are done, it’s not too far from completion.

Pool has been tiled and is being tested.

Clubhouse

We are finally getting there with the design.

Works are expected to be started soon. Most of the works will be quick.

Furniture and fittings have all been ordered.

Update July 2018

Blocks C & D

We are still making good to some areas, and just commissioning and cleaning areas and working with the hotel GM and teams to make sure we are all on the same page. Everything is working well.

The hotel has also written up a list of works that need to be done, all of which improve the rooms and the external areas.

Works to the basement areas are not yet complete but are moving on. Progress is being made.

Block F

Block F is moving on well and very active. All trades are being coordinated to ensure the most progress possible.

Works ongoing are MEP, ceilings to corridors, tiling, painting, installation of sanitary wares, remaining block works to the external walls, and rendering. Two floors are complete for external doors and windows.

Furniture works are handled off-site. Installation will begin later next month.

Villa

Works are ongoing on par with the X Suites, with ceilings and tiling as well as painting underway.

The next step will be the furniture works.

X-Suites

Ceilings are installed.

MEP and tiling works have begun.

External door frames have been installed.

Clubhouse

Still at the final design stage.

The Beach Front: Update July, August, and September 2018

Leave a Reply

Your email address will not be published. Required fields are marked *