The Beachfront: Updates for April 2019
Construction Update: 25 April 2019
The main construction work is complete. There are only some minor works left before the hotel opens next month.
Blocks A & B
A & B buildings – The entrance lobby for both buildings are now completed with sand wash finishing. The gate to the building is now being plastered. Roof work will commence shortly.
Restaurant Building F
Above are 3D rendered pictures. Below are the actual on-site images.
Building F (Restaurant) – Restaurant lighting installation has started. Tempered glass has been installed at the entrance at the front of restaurant. Roof work installation in front of the restaurant has started.
Beach Bar/Clubhouse
Clubhouse – This week the furniture and interior decoration has started at the beach bar (clubhouse). They started to install the wood panel for the wall.
Update for the Week of April 11
Blocks A & B
Both blocks now have lobby entrance works underway.
The wall is cut for the main gate from behind the lobby.
The sand-wash for the building walk-way is complete.
Lobby
Above are the 3D rendered pictures. Below are the real pictures on-site.
The lobby renovation now finished. The wall, lighting, and ceiling are now fully installed.
There are some additional decorations to be added to the lobby after handover from the contractor.
Restaurant Block F
Above are the 3D rendered pictures. Below are the real pictures on-site.
The decorative wood ceiling has been installed.
The wall decoration is finished.
Some touch-up work on the ceiling and the counter is still required.
Beach Bar/Clubhouse
Clubhouse – plastering and ceiling installation now finished.
The restaurant glass panel is now installed.
The Signature Villas
Signature Plot 11
Blocks A & B now have lobby entrance to both buildings.
Lobby
Decorative wall panels have been installed.
The marble floor has been replaced.
Clubhouse / Bar
Blockwork for the bar counter, and the panel for flower pot installation is underway.