Main construction work is complete. Only some minor additional works to complete before hotel opening next month.

The project road is now finished. Trees and flowers have been planted along the side of the building.

Lobby- The hotel staff are now working in the lobby. GM plans to finish all additional work for the lobby by the end of May.

Buildings A & B – The swimming pool for buildings A & B has fully run. Above is a sample of room number signage in building B.

Buildings C & D

Landscaping work started last week in the swimming pool area and in the front of fitness room is now completed. The building entrance landscaping work is progressing well.

(Above) Completed landscape work in the front of fitness center.

Building D entrance progress (above left) and C (right).

Building F (Restaurant) – Furniture has now been delivered. The paintwork at the front of restaurant is complete. “The Quest” restaurant signage is now installed.

Building F (Landscape) – Tree and flower landscaping is now complete.

Beach Bar/Club house

Above – Front view of the beach bar. Right – Artificial wood floor walkway to the beach.

Beach Bar/Club house – The beach bar has progressed well this week. The concrete column is now covered with artificial wood, and the bar counter has been decorated. Outside the bar cladding to support the plant and flower pots has been installed.

X-Suite
Built-in furniture work is underway for all 4 units. Beds and cabinets are now installed.
The Beach Front: Updates 16 May 2019