The main construction work has finished. Only minor additional works to complete before the hotel opens next month.

The main hotel road is finished. Lighting has been installed on the walls along the road. Equipment required for hotel operation has been purchased.

Buildings  A & B – Not much additional work required to complete buildings A & B; just the additional roof for the entrance of the building. This week the wall of the outdoor shower was cut down. The previous one was too high.

Buildings C & D


(Above) Swimming pool tempered glass railing.


Buildings C & D – Works to complete: 1) Swimming pool tempered glass rail installation. 2) The staircase for building entrance (just started this week).

Restaurant Building F


Above are the 3D rendered pictures. Below are the real on-site images.




Building F (Restaurant) – Decoration work is finished. The glass door and air-curtain are now installed at the front door. Only some minor touch-up work to complete before the chairs and tables are delivered.

Beach Bar/Club house



Beach Bar/Club house – The furniture and interior decoration has a progressed well. Glass panel installation completed. Wood panel installation underway.

Villas


Interior decoration has not yet started. Only the boundary fence with the hotel and land next door completed this week.

The Beach Front: Updates May 2019